Century-Old West Tremont Avenue Step Street Restoration Complete

The Step Street renovation took approximately two years to complete. On April 7, 2020, the Department of Design and Construction and the Department of Transportation announced that the restoration of West Tremont Avenue Step Street, connecting Cedar Avenue to Sedgwick Avenue, has been completed. The project was funded by Transportation and managed by Design and Construction. The restoration of the century-old stairs cost $7 million.


Rosedale Infrastructure Upgrades to Be Completed Ahead of Schedule

The project is set to be completed one season early and over $1 million under budget. On March 4, 2020, the NYC Department of Environmental Protection announced that a major infrastructure upgrade project in Rosedale, Queens, would be completed ahead of schedule. The area, from 130th Avenue to the north, 133th Avenue to the South, and Brookville Boulevard to the west, is part of an area in southeast Queens that has faced flooding in the <Read More>