City Comptroller Audit Finds DOB Failed To Fully Implement Crane Safety Report

In four years, Buildings has enacted eight of sixty-five safety recommendations after spending $5.8 million on a study. On November 7, 2014, New York City Comptroller Scott Stringer released an audit finding the Department of Buildings has failed to act upon recommendations for crane safety that came from a report they commissioned, four years after the report was issued.


Audit Faults Control of Field Inspectors

Comptroller’s Audit Reveals Multiple Deficiencies in how Buildings Oversees Field Inspectors. 

On December 21, 2018, Comptroller Scott M. Stringer published an audit of Department of Buildings’ oversight of its field inspectors that covered the period of July 1, 2016 to December 31, 2017. The audit reviewed the oversight of 86 field inspectors working in six units: the Building Enforcement Safety Unit, the Special Operations unit, each of Brooklyn and Queens’s Construction Enforcement units, and each … <Read More>


Comptroller Finds Buildings Needs to Improve the Site Safety Professional Licensing Process

On June 30, 2016, New York City Comptroller Scott Stringer’s office released a Report on the Department of Buildings’ issuance of licenses to site safety professionals. There are two types of site safety professional licenses: site safety manager and site safety coordinator. City law requires that a site safety manager be onsite to oversee all work of any project to demolish or construct buildings 15 stories or more in height, and a site safety coordinator … <Read More>


Report Identifies Flaws in DOB’s Auditing of Professionally Certified Applications

Comptroller’s audit found that Buildings generally implemented adequate controls over construction permit applications, but issued three recommendations to ensure public safety. On June 17, 2016, the Officer of the Comptroller Scott Stringer released a report of an audit conducted on the Department of Buildings’ processing of construction permits. The audit determined that Buildings’ controls for the processing of application were implemented consistently, that there were appropriate separation of duties, and an adequate application tracking system. … <Read More>