Contractor denied additional payment

DEP required Jett Industries to clean channels at the Wards Island Wastewater Treatment Plant; Jett claimed that cleaning was extra work and sought an additional payment. Jett Industries, Inc. entered into an $116,969,000 contract with the Department of Environmental Protection to rehabilitate the settling system at the Wards Island Wastewater Treatment Plant. During the bidding process DEP, in response to bidders’ questions regarding the cleaning of tanks and channels, notified bidders that contractors were advised … <Read More>


Bridge delay claim denied

Tutor Perini sought §22,941,971.68 for a two-year delay caused by a court injunction. In 2013, Tutor Perini Corporation entered into a $102 million contract with the Department of Transportation to replace the City Island Road bridge that spans Eastchester Bay between the Bronx and City Island. A state court injunction delayed the construction of the bridge for two years and forced the redesigning of the bridge.


Extra Payment for Repair Work Denied

Contractor sought compensation for repairing damages caused during an additional work contract. In 2009, Sanitation entered into a $161 million contract with Prismatic Development Corporation to improve the North Shore Marine Transfer Station in Queens.  Prismatic, following Sanitation’s plans and specifications, installed a new deck and concrete overlay on the Transfer Station’s exterior ramp.  The concrete overlay later developed extensive cracking.  Sanitation conceded that an error in the design documents provided by Sanitation to Prismatic … <Read More>


Subcontractor’s Claim Against Prime Contractor Upheld

Prime contractor agreed to process subcontractor’s extra work claim, but failed to file a timely claim. The Department of Sanitation in 200 awarded a contract to Arnell Construction Corp. to build two new sanitation garages for Districts 1 and 4 located at 161 Varick Street in Brooklyn. Arnell then signed a $3 million subcontract with Rad & D’Aprile, Inc. to perform masonry work on the project.


Homeowner’s Cash Award Remanded

Homeowner claimed home improvement contractor did incompetent work. Favors and Company Inc., a home improvement contractor, and Edmina Lee, a homeowner, entered into a series of home improvement contracts to make repairs for her two properties located at 112-28 199th Street and at 186-21 Hilburn Avenue, Queens. Work related to the 199th Street property occurred between April 28, 2014 and May 23, 2014. Work related to the Hilburn Avenue property occurred between May 15, … <Read More>


Audit Faults Shelter Contracts

State Comptroller’s audit criticized the high costs of past homeless shelters leases; the agency responded that it is in the process of tightening its leasing procedures. In October of 2017, the New York State Comptroller’s office released an audit regarding contracts signed over the past four years between the City and landlords providing homeless shelters. The audit found that the Department of Homeless Services does not have written policies and standard operating procedures for key … <Read More>