DOB’s denial of Staten Island permit overturned

Developer proposed unique design to exploit loophole in zoning text. Fred Corono applied for a building permit to add a second building in the rear of his oversized 6,938- square-foot lot in Staten Island. The Department of Buildings denied the application, believing that Corono specifically designed the new building to evade the requirements of the City’s Lower Density Growth Management zoning restrictions. The controls, enacted in 2004, set strict size and yard limits on proposals … <Read More>


Text Amendments Approved

Follow-Up Corrective Action (FUCA) approved 17 modifications to Hudson Yards revitalization plan. In January 2005, after extended negotiations, the City Council approved ten land use actions related to the revitalization of Manhattan’s Hudson Yards. 2 CityLand 4 (Feb. 15, 2005). Public review of the proposed text amendment identified the need for certain modifications. On August 4, 2005, the Planning Department, Council Member Christine Quinn, and Manhattan Community Board 4 applied jointly to incorporate the modifications … <Read More>


GUEST COMMENTARY: The City of Yes – NYC is Taking Leadership on Energy Storage System Siting

 

by Caroline G. Harris, Esq. Goldman Harris LLC and Eric Vath, Esq. Goldman Harris LLC

To meet the climate goals of the 2016 Paris Agreement, New York State and New York City have adopted aggressive energy efficiency goals.  The Mayor’s 2022 City of Yes program announced numerous initiatives to make the city sustainable, resilient and equitable.  One of them, the City of Yes: Carbon Neutrality, aims to reduce our reliance on carbon-based fuels by … <Read More>


Mayor Announces “Get Stuff Built” Plan to Streamline Building and Land Use Processes

On December 8, 2022, Mayor Eric Adams unveiled New York City’s latest land use roadmap, Get Stuff Built, a complement to his City of Yes zoning proposals announced earlier this year. Get Stuff Built represents a collaborative effort among more than two dozen agencies serving on the Building and Land use Approval Streamlining Taskforce (BLAST), which held 18 working group sessions and four roundtable discussions with more than 50 external stakeholders. Designed to address … <Read More>



Contractor denied $2.5 million claim

Plumbing company claimed time extension due to delays. In May of 2012, the New York City School Construction Authority awarded BG National Plumbing & Heating Inc. a contract to perform accessibility and electrical upgrades for the New York City School Construction Authority. When it became evident that BG Plumbing could not meet the contractual deadline, BG Plumbing filed a notice of claim with the City alleging it was entitled to an extension because of certain … <Read More>