BSA overturned on Queens vested rights case

Buildings made initial error in not issuing building permit. In 2003, Hamida Realty sought plan approval from the Department of Buildings for two, three-family homes on two adjacent lots that would share a foundation and a common wall. Buildings approved the plans, but Hamida waited over a year to apply for permits. When it applied, Buildings granted the permit for one building, but held the second permit, erroneously requiring Hamida to submit a site safety … <Read More>


Federal court rejects challenge to Yankee Stadium

Bronx locals’ second attempt to halt Yankee Stadium claimed bias and ineptitude on the part of the National Parks Service. As part of the needed approvals for the Yankee Stadium development, the National Park Service approved the plan to privatize a 10.67-acre portion of the Macomb’s Dam Park and replace the lost park space with 16.44 acres on three separate parcels, including the old Yankee Stadium site, to be developed with baseball and softball fields, … <Read More>


Court affirms approval of Brooklyn Sanitation garage

Property owners and neighboring residential buildings sued to stop Sanitation garage. The Second Department affirmed the lower court decision of Justice Abraham Gerges dismissing claims brought by property owners, nearby businesses and residents objecting to the condemnation of land in Clinton Hill, Brooklyn for construction of a Sanitation truck garage. 1 CityLand 48 (Dec. 2004).

The court found the parties’ claims untimely since their challenges to the condemnation were entirely based on the land use … <Read More>


Challenge to East 91st transfer station rebuffed

Community claimed the FEIS flawed, the project was a nuisance and a Bronx facility would be more economical. In June 2005, Sanitation obtained final City approval for construction of a marine transfer station on the site of an inactive waste transfer station at East 91st Street and the East River. The approval was part of a citywide proposal to make each borough responsible for the export of its own waste. Sanitation’s proposal to reactivate the … <Read More>


NYU East 12th Street dorm construction can proceed

Construction work can continue on new 26-story NYU dorm, which will incorporate the front tower of St. Ann’s Church. Photo:Morgan Kunz.

Court denied request to stop construction while residents file BSA appeal. East Village residents sought an injunction to stop construction of a 26-story dormitory for New York University on an East 12th Street site occupied by the vacant and partially demolished St. Ann’s Catholic Church.

Hudson 12th Development LLC purchased 120 East 12th Street, … <Read More>


Court denies owner’s motion to increase appraisal

First appraisal allegedly based on flawed calculation under City’s Zoning Resolution. Malba Cove Properties, Inc. had owned a 655,188- square-foot undeveloped parcel in College Point, Queens that the City acquired by eminent domain in 1996 as part of the City’s plan to develop a waterfront park.

With the trial on the property value set to start in mid-July 2006, Malba asked the court in late May for permission to file a revised appraisal that would … <Read More>